A newly completed apartment can look flawless at an inspection while the building has expensive problems that are difficult to see. Waterproofing failures, defective fire-safety systems, façade problems, drainage issues and structural defects often concern shared parts of the building rather than the individual apartment. Purchasers therefore need to look beyond the floor plan, finishes and display suite. The important question is not simply whether an apartment is new; it is what the purchaser can establish about construction quality, the owners corporation’s finances, the available defect protections and the contract before becoming legally bound.
This is particularly relevant to purchasers considering new and recently completed strata developments in Marrickville, Dulwich Hill, Alexandria, Newtown and other parts of Sydney. Different buildings can have very different construction histories, insurance arrangements and defect risks. The checks below are a starting point for deciding which enquiries to make; they cannot establish the condition of any particular building.
Why common-property defects matter to an individual owner
A buyer may inspect the lot, check that the appliances work and commission a building inspection of the apartment. Yet a defect in a basement membrane, common roof, external wall, fire door or drainage system may create costs that are eventually borne by all lot owners. The owners corporation generally has responsibilities concerning the common property, but the source of funds and the prospects of recovering defect costs can be uncertain. A significant special levy can change the economics of an otherwise attractive purchase.
The apartment’s purchase price is only one component of ownership cost. Before exchange, ask about existing levies, the capital works fund, planned major repairs, defects under investigation, expert reports and any dispute with the developer, builder or insurer. A recently painted lobby is no substitute for understanding the maintenance and building history. Equally, a disclosed problem is not necessarily a reason to walk away if its nature, repair plan, funding and contractual consequences are properly understood.
Understand three different NSW protection mechanisms
There are three distinct concepts which are sometimes treated as though they provide the same protection. Statutory warranties under the Home Building Act 1989 can give eligible owners rights concerning residential building work. The ordinary periods are generally six years for a major defect and two years for other defects, subject to the statutory rules about completion, classification and limited extensions. Identifying the applicable period and respondent is a legal question; the warranty is not an automatic repair service.
The Strata Building Bond and Inspections Scheme involves a developer-provided building bond and prescribed inspections in eligible strata developments. The bond is intended to support rectification of identified defects, but it is limited and is not a guarantee that every repair will be paid for. The process, inspection reports and status of any bond are important records. The NSW Government describes the bond as 2% of relevant construction contract costs; buyers should verify the applicable scheme requirements for their development.
Decennial liability insurance, commonly called DLI, is different again. Since 20 August 2026, an eligible policy covers ’relevant defects’ in the building elements of the common property for ten years from first occupation, subject to the policy terms. Broadly, these are defects that cause, or are likely to cause, damage to the building or a risk of death or serious injury. Coverage is linked to the building and not simply to the developer’s continued existence. However, not every project has a DLI policy, and not every defect is covered. Purchasers should request actual evidence of the policy, insurer, coverage and claims process rather than accept the phrase ’ten-year insurance’ in an advertisement.
What is scheduled to change from 1 December 2026?
NSW has announced a change to insurance requirements for new construction of class 2 apartment buildings containing more than two sole-occupancy units. From 1 December 2026, eligible developments will generally move away from Home Building Compensation insurance requirements and instead use the strata building bond framework or DLI, where the relevant conditions are met. Projects that commenced earlier and already obtained the required Home Building Compensation insurance may retain that arrangement. The legal classification of the building and the timing of construction matter.
For purchasers buying off the plan, this makes the contract and disclosure material particularly important. The NSW Government has identified a requirement for affected developers to notify certain off-the-plan purchasers about the altered arrangements by 31 December 2026. A purchaser should not assume the new regime automatically grants ten years of coverage, applies retrospectively to every existing apartment or removes the need for independent due diligence. Check the current requirements before relying on them for a particular contract.
The documents to obtain before exchanging contracts
For an established strata scheme, useful enquiries may include the strata roll, meeting minutes, financial statements, capital works fund forecast, current levy notices, special levy history, building defect reports, engineering advice, correspondence with the developer, court or tribunal proceedings, and any compliance orders. Check the strata insurance documentation, but remember that ordinary strata building insurance is not equivalent to a statutory warranty, building bond or DLI policy.
For a new or off-the-plan purchase, the emphasis changes. The purchaser should review the contract, prescribed disclosure documents, specifications, plans, estimated levies, completion arrangements, sunset clauses and any variations the developer may make. Ask for information about building approvals, occupation certificates, the builder and developer, the applicable building bond or insurance mechanism, and any available inspection reports. If the contract is being exchanged before completion, the buyer may not yet have access to all the records that would exist for a finished scheme; this uncertainty should be understood and addressed in the contract review.
What should you look for in strata meeting minutes?
Minutes can reveal concerns that are not obvious from a summary strata report. Repeated complaints about water leaking into basement storage, unresolved waterproofing in bathrooms, lift failures, fire-safety notices, disputes over defects or unexpectedly large quotations are reasons to investigate further. A minute saying an issue is ’under review’ is not the same as evidence that repairs have been funded and finished. Ask whether any expert has attributed the problem to defective construction, normal wear, maintenance or a combination of causes.
Consider the owners corporation’s ability to meet its expected obligations. A new scheme may have only a small capital works fund because few levies have yet been collected. That alone is not necessarily alarming; however, optimistic budgets or missing maintenance forecasts may make future levies difficult to estimate. If the proposed purchase depends on rental income or a tight household budget, test the effect of higher levies rather than assuming the advertised figure will remain constant.
Should a buyer commission independent inspections?
The answer depends on the property’s age, type and available evidence. An ordinary inspection focused on the individual lot may miss waterproofing behind walls, concrete or fire-safety defects in common areas and non-compliant work that requires specialist testing. A suitably qualified building consultant or engineer can advise on the limits of a proposed inspection and whether additional reports are justified. Where the property is in a small strata scheme, shared walls, roof or drainage infrastructure can be particularly important.
Specialist investigations cost money, but they may be proportionate when the potential exposure is substantial. The proper question is whether the available material gives the buyer enough confidence to exchange. Legal advice can explain what rights and enquiries the contract supports; technical advisers identify the physical condition and likely remediation options. Neither discipline substitutes for the other.
What if a defect is discovered after settlement?
A defect does not automatically mean that the purchaser personally has a claim against the builder, or that the developer must immediately fix it. The answer may depend on who owns the affected building element, which warranties apply, the building’s completion date, the insurance or bond mechanism and whether relevant proceedings have already commenced. Delay can be costly where limitation periods or scheme deadlines are running. A buyer or owners corporation may need technical evidence before deciding how to proceed.
Before exchange, ask about known disputes and whether the owners corporation has obtained legal advice about any claim. A buyer acquiring a lot during an unresolved dispute needs to understand what has been disclosed, what financial commitments may follow and whether special levies or litigation costs are likely. Avoid treating a developer’s verbal assurance that a defect is ’minor’ as a substitute for written independent evidence.
Seven practical questions to ask before buying
First, when was the building completed and what building class applies? Second, what does the strata records inspection reveal about defects and repairs? Third, is there a current building bond, relevant DLI policy or other insurance arrangement, and can the actual documents be produced? Fourth, have experts issued reports about water, structure or fire safety? Fifth, are there pending proceedings, compliance orders or special levies? Sixth, what are the estimated running costs, and could they rise significantly? Seventh, does the sale contract provide appropriate disclosure and protections for this particular transaction?
How CM Lawyers can assist
CM Lawyers assists apartment buyers with conveyancing, strata-related due diligence and pre-exchange contract reviews in Marrickville and across Sydney. A review can identify provisions that need attention and help the purchaser decide whether to make additional enquiries or obtain specialist building advice. The objective is an informed decision before exchange, when there may still be an opportunity to negotiate or reconsider the purchase.
If you are buying a new or recently completed apartment, contact CM Lawyers on (02) 9557 9000 to arrange a paid contract review. This is general information, not advice about any particular building, insurance policy or legal claim.
Related reading
- What the October 2026 NSW strata reforms mean for Inner West buyers
- Limited inspections in off-the-plan purchases
- Buying a strata unit in NSW
Image: Wolli Creek apartment buildings at sunset by Maxim75, CC BY-SA 4.0, via Wikimedia Commons.